Road Construction - August 20 to 24
Contractors may be working on the following arterial and collector streets from August 20th to 24th under the City’s annual streets rehabilitation and infrastructure maintenance programs. Work could include concrete/street excavation, concrete work, paving, heater scarifying, utility adjustment, ditch cleaning and culvert installation. Commuters may experience traffic delays in these areas:
Bonaventure Avenue (Military Rd. to Merrymeeting Rd.)
Long's Hill
Mundy Pond Road (St. Theresa's Church to Blackler Ave.)
Pennywell Road (Cashin Ave. to Ropewalk Ln.)
The Boulevard (Kings Bridge Rd. to Carnell Dr.)
Torbay Road (Stavanger Dr. to Rona)
Commuters may also experience traffic delays and should be wary of milled asphalt areas due to grind and patch operations on the following streets:
Bay Bull's Road
Bennett Avenue
Blackmarsh Road
Brookfield Road
Captain Whelan Drive
Columbus Drive
Cowan Avenue
Crosbie Road
Freshwater Road
Old Pennywell Road
Old Petty Harbour Road
Pearltown Road
Rickett's Road
Ruby Line
Southlands Blvd.
St Clare Avenue
Stamps Lane
Other local/residential streets may have ongoing construction and affected homeowners and businesses have been notified separately.