Street Rehabilitation - Aug. 19 to 23

Location: 
Various locations
Start Date: 
Monday, August 19, 2013 - 7:00am to Friday, August 23, 2013 - 10:00pm

Below is a list of the streets the City plans to work on next week (August 19 to 26, 2013) under its street rehabilitation program. Commuters may experience traffic delays in these areas.

Street Rehabilitation
(Work could include Concrete/Street Excavation, Concrete Work, Paving, Heater Scarifying, Utility Adjustment, Ditch Cleaning and Culvert Installation)
Bay Bulls Road - Ruby Line to Old Bay Bulls Road Intersection
Winchester Street
Elm Place
Sycamore Place
Prince Phillip Drive - Allandale Road to Clinch Crescent
MacDonald Drive - Portugal Cove Road to Torbay Road
Torbay Road - McDonald Drive to Elizabeth Avenue
Whiteway Street - Newtown Road to Guy Street
Calver Avenue - Aldershot Street to Mayor Avenue
Bell's Turn - Higgin's Line to Hunt's Lane
Freshwater Road - Crosbie Road to Stamps Lane
Forest Road - Civic #173 to Cuckhold's Cove Road
St. Clare Avenue (Smith Avenue to Golf Avenue)
Pennywell Road (Golf Avenue to Cashin Avenue)
Sinnott Place
Columbus Drive – Captain Whelan Drive to Blackmarsh Road
Columbus Drive – Pennywell Road to Empire Avenue (South Bound)
Brownrigg Place

Grind and Patch Operations
Torbay Road
McDonald Drive
Prince Phillip Drive
Bannerman Road
Prescott Street
Duckworth Street
Water Street
Queens Road