Streets Rehabilitation

Location: 
Various Locations
Start Date: 
Monday, November 9, 2015 - 7:00am to Friday, November 13, 2015 - 10:30pm

The City will be working on the following streets from Nov 9-13 under the street rehabilitation program.  Commuters may experience traffic delays in these areas.

Street Rehabilitation
(Work could include Concrete/Street Excavation, Concrete Work, Paving, Heater Scarifying, Utility Adjustment, Ditch Cleaning and Culvert Installation)
 
Bates Hill
New Gower Street
Water Street
Water Street (Sudbury Street to Waterford Bridge Road)
Lemarchant Road (Cookstown Road to Lime Street)
Back Line Road (Durdle Drive to Della Drive - Grind & Patch)