Traffic Disruption – Carrick Drive

Location: 
Carrick Drive – Paul Reynolds Center
Start Date: 
Monday, June 27, 2016 - 8:15am to Wednesday, August 31, 2016 - 4:00pm

Motorists and pedestrians are advised that On Monday, June 27 contractors will begin construction of a new entrance to the facility off Carrick Drive that will include the installation of a simple roundabout to smooth traffic flow in the area.
Road construction will occur during the day and will impact the sidewalk on the community-centre side of the street as well as lane reductions. Seeking an alternate route is recommended during the summer months, and the City apologies to residents for the disruption.
 
The new road configuration is scheduled to be in operation before the start of the 2016-2017 school year; public information and education on using the new roundabout will begin in August as the road nears completion.
The City of St. John’s apologizes for any inconvenience. 

If you require further information, please contact Access St. John's at 311 or 754-CITY
(2489).